Introduction

Stockyard Hill Wind Farm is a nominal 532 MW wind farm. 

Construction of the wind farm incorporates a diverse range of activities, including manufacture, delivery and erection of 149 3.x MW wind turbine generators, bulk earthworks and internal road construction (approx. 110km), public road modifications, construction of wind turbine foundations (inclusive of concrete, reinforcing steel & hold down assemblies), trenching and laying cable for underground electrical reticulation systems, substation construction (inclusive of power transformers, switchyard, electrical protection systems, switchrooms & substation automation system), high voltage export transmission line, lattice tower meteorological monitoring masts, construction of operations facility buildings and associated consulting services (environmental, geotechnical, design).

The project will be executed via a turn key EPC (Engineer Procure Construct) carried out by Goldwind Australia Pty Ltd who will be responsible for 2 main workstreams; 1) Supply and Install of Wind Turbines, and 2) Balance of Plant or BoP (roads, on site electrical etc). The BoP workstream will be subcontracted to a Procurement Entity who will in turn sub-contract out various work packages. 

The appointment of the BoP Procurement Entity is expected to occur in Q4 2017, with detailed pre-qualification and tendering of various work packages and construction work commencing on site in Q1 2018. The project is expected to be connected to the electricity grid by Q1 of 2019 with all turbines operational by the end of Q1 2020.  Work shall be carried out according to the following general prequalification criteria and standards noted at the end of this page.

 

Various minor subcontracts / suppliers

Suppliers interested in smaller work packages (<$1Million in value) should register their interest in SHWF via the Moorabool ICN gateway page. Suppliers already registered via the Morrabool page need not do so again for SHWF. 

Work packages noted on the Moorabool page are:

  • Arborists           
  • Bin/Skip Supply
  • Building contractor (operations and maintenance buildings)       
  • Civil construction of onsite roads, crane hardstands and foundations             
  • Cleaning Services
  • Concrete Supply
  • Diesel supply for machinery
  • Earth moving and construction equipment                       
  • Electrical Wholesalers
  • Fencing Contractors      
  • Fire alarm & Fire Extinguisher services & safety testing (test & tag)             
  • Formwork and steel fixing          
  • General Crane Hire        
  • Geotechnical Testing     
  • High Voltage Commissioning and safety testing  
  • Hire Equipment
  • Hospitality: Events, Functions and Catering, and Accommodation             
  • Household/Office Furniture and Appliance Providers      
  • Landscape Designers and Landscape Contractors                           
  • Low Voltage Electrical Works     
  • Moorabool Wind Farm - Any Other Opportunities           
  • Plumbing Works                           
  • Quarry Products                           
  • Roads
  • Scrap metal dealers       
  • Security Services
  • Signwriters and signage supplies             
  • Surveying Services         
  • Toilet pump out services            
  • Training, Occupational Health & Safety & First Aid           
  • Vehicle and 4X4 hire     
  • Waste collection and toxic substance removal   
  • Water carting services

 

Major subcontracts / suppliers

The Following Work Packages are noted on the Stockyard Hill ICN gateway for major packages of work associated with Stockyard Hill Wind Farm:

  • Building Construction
  • Bulk Earthworks
  • Civil Construction
  • Concrete Supply
  • Cranage and Erection
  • Design Services
  • Hold Down Bolt Supply
  • HV and MV Electrical Equipment Supply
  • HV Transmission Line Construction
  • Logistics Services
  • Reinforcing Steel Supply
  • Trenching and Cable Laying
  • Wind Turbine Support Towers

Contractors and Consultants who would like to register their interests for the above work packages should click here on the SHWF ICN Gateway Page.

 

Contact details

Contact Details for Key Procurement Officers will be notified below in Due Course:

  • Stockyard Hill Wind Farm – Justin Howes - 1800 753 730 - stockyard@goldwindaustralia.com
  • Goldwind Australia – TBA upon Contract Commencement
  • Major Balance of Plant Contract - TBA upon Contract Commencement

 

General prequalification criteria

As noted in the Introduction section Stockyard Hill Wind Farm will be constructed 2 main workstreams; 1) Supply and Install of Wind Turbines, and 2) Balance of Plant or BoP (roads, on site electrical etc). Prior to engagement, companies will be required to complete a detailed prequalification approval according to the requirements of the hiring company.  However, all suppliers shall meet the following general requirements:

Health and Safety:

 

Workmanship:

 

Environmental:

 

Workstandards

All project work shall comply with applicable local codes and standards, including, but not limited to the relevant standards and codes of practice of the Standards Association of Australia or where relevant local standards and codes of practice do not exist the relevant standards and codes of practice of the, IEC or ISO. All suppliers shall, as part of the Contractor’s Documentation provide a list of Applicable Standards as identified by the Contractor as being relevant to the Works. 

The Works shall comply with all applicable industry codes, including, but not limited to the following:

  • AS 1012 Methods of testing concrete     
  • AS 1275 Metric screw threads for fasteners        
  • AS 1319 Safety signs for the occupational environment
  • AS 1379 Specification and supply of concrete     
  • AS 1429.1          
  • AS 1470
  • AS 1554 Structural steel welding Set
  • AS 1554.3          
  • AS 1657 Fixed platforms, walkways, stairways and ladders - Design, construction and installation
  • AS 1735
  • AS 1768             
  • AS 1824             
  • AS 2067             
  • AS 2067 Substations and high voltage installations exceeding 1 kV a.c.             
  • AS 2865 Confined spaces            
  • AS 2870             
  • AS 3000 Electrical installations (known as the Australian/New Zealand Wiring Rules)    
  • AS 3008.1.1       
  • AS 3600             
  • AS 4142.3          
  • AS 4325.1          
  • AS 4702             
  • AS 5000.1          
  • AS 5100             
  • AS 60076           
  • AS 60529-2004 Degrees of Protection provided by enclosure      
  • AS 61000           
  • AS 62040 Uninterruptible power systems (UPS) 
  • AS 62271           
  • AS ISO 10002-2006 Customer satisfaction - Guidelines for complaints handling in organizations
  • AS/ACIF Standard S009 
  • AS/NZS 1170 Structural design actions   
  • AS/NZS 1768     
  • AS/NZS 1891 Industrial fall-arrest systems and devices   
  • AS/NZS 2312:2002 Guide to the protection of structural steel against atmospheric corrosion by the use of protective coatings
  • AS/NZS 3000 Electrical installations (known as the Australian/New Zealand Wiring Rules)   
  • AS/NZS 4488     
  • AS/NZS 4671     
  • AS/NZS 4671 Steel Reinforcing Materials             
  • AS/NZS 4672     
  • AS/NZS 4672 Steel Prestressing Materials           
  • AS/NZS 4801     
  • ASTM C109MAustralian Certification Authority for Reinforcing Steels Ltd (ACRS)         
  • DNVGL-ST-0126 (2016) Support Structures for wind turbines      
  • EC 61400-12-1  
  • ENA EN1-2006 Substation Earthing Guide           
  • HB100(CJC4)     
  • IEC 60287                        
  • IEC 60287-3-2 Economic Optimisation of Power Cable Size           
  • IEC 61400-1 Wind Turbines
  • IEC 62035-3       
  • IEC 62305          
  • IEC61400-12-1 Ed 1.0
  • ISO 12944 Paints and varnishes - Corrosion protection of steel structures by protective paint systems Set of Standards 
  • ISO 14001          
  • ISO 9000            
  • National Construction Code (of Australia)           
  • National Electricity Rules